Analisis Tingkat Efektivitas Plant Pabrik XYZ Menggunakan Overall Equipment Effectiveness (OEE)
Authors | ||
Issue | Vol 7 No 1 (2024): Talenta Conference Series: Energy and Engineering (EE) | |
Section | Articles | |
Section |
Copyright (c) 2024 Talenta Conference Series: Energy and Engineering (EE) This work is licensed under a Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License. |
|
Galley | ||
DOI: | https://doi.org/10.32734/ee.v7i1.2224 | |
Keywords: | Cause and Effect Diagram Efektivitas Mesin dan Peralatan Overall Equipment Effectiveness Effectiveness Machines and Equipment | |
Published | 2024-10-22 |
Abstract
PT XYZ merupakan perusahaan agrobisnis yang bergerak dalam distribusi dan pemasaran pupuk bagi petani di seluruh wilayah di Indonesia. Target produksi tahunan PT XYZ dapat dicapai dengan adanya kelancaran kegiatan proses produksi. Salah satu faktor utama dalam kegiatan proses produksi adalah, kondisi mesin produksi dan peralatan pendukung lain. Berdasarkan pengamatan dan analisis yang dilakukan ditemukan bahwa rate produksi pupuk pada Plant I lebih rendah dibandingkan dengan Plant II. Oleh karena itu salah satu faktor utama yang dianalisis lebih lanjut adalah kinerja Plant I yang dilihat dari tingkat efektivitas mesin dan peralatan dengan menggunakan perhitungan kinerja dengan Overall Equipment Effectiveness (OEE). Hasil analisis menunjukkan bahwa nilai Overall Equipment Effectiveness terendah ada pada bulan Desember dengan nilai OEE sebesar 74% dengan kategori nilai Passable. Selain itu pada Januari, Maret, Mei, Juli, dan November diperoleh kategori nilai Pretty Good. Indikator utama yang mempengaruhi nilai ini adalah pada nilai Availability dan Performance. Penyelesaian atas permasalahan yang ada dilakukan dengan menganalisis faktor penyebab dengan menggunakan diagram sebab akibat dan metode 5W+1H serta memberikan usulan perbaikan yang dapat dilakukan.
PT XYZ is an agribusiness company engaged in the distribution and marketing of fertilizers to farmers across Indonesia. The annual production target of PT XYZ can be achieved with the smoothness of production process activities. One of the main factors in production process activities is the condition of production machines and other supporting equipment. Based on observations and analyses conducted, it was found that the fertilizer production rate at Plant I was lower compared to Plant II. Therefore, one of the main factors to be further analyzed is the performance of Plant I, viewed from the effectiveness level of machines and equipment using performance calculations with Overall Equipment Effectiveness (OEE). The analysis results indicate that the lowest Overall Equipment Effectiveness value occurred in December with an OEE value of 74% in the Passable value category. Additionally, in January, March, May, July, and November, the Pretty Good score category was obtained. The main indicators influencing this value are the Availability and Performance values. Resolution of existing problems is carried out by analyzing causal factors using cause and effect diagrams and the 5W+1H method, also providing suggestions for improvements that can be made.